We’re excited to share the latest updates on our Odon, Indiana facility. Our team has been making significant progress, and we’re on track for our planned milestones.
Packaging Assembly Cleanroom:
- Complete and ready for manufacturing
- Fully staffed
- BKM (best known methods) unit processes established
Main Manufacturing Cleanroom:
- Advanced packaging manufacturing
- 2.5D/3D with HI (heterogeneous integration)
- Many manufacturing and development tools already on site
- More tools arriving each week
- On schedule for full facilitation by August 2024
- On schedule for production by January 2025
- Extensive cleanroom space with class 100 ratings
Infrastructure:
- 30,000 sq.ft. plant
- Upgraded megawatt power
- High flow rate deionized water plant
- External gas farm
- High capacity air handlers
- Backup power generation
Operations:
- Local ecosystem being developed
- Collaboration space for R&D and university institutions
- ISO certification process underway
Construction Photos from May of 2024
Concrete slab is poured:
AMAT Raider arrives:
Sewer lines are installed:
Main cleanroom and gowning room are framed:
For a panoramic drone video of the Odon facility, see our Facebook post!